rendering: Looking northwest at the proposed reservoir
embankment from Oso Parkway. |
Should the SMWD Board of Directors approve plans for the
Upper Chiquita Reservoir, construction would likely commence
later in the year. Engineers anticipate that (pending timely
approval) the reservoir will be operational prior to the next
scheduled shutdown of the Diemer Filtration Plant in Yorba
Linda in 2010.
Completion of the reservoir is expected to take 26 months
and would include reservoir site development, piping installation,
chemical storage construction and pump station construction.
It is estimated that 25 to 60 workers will be employed during
construction activities.
 |